The Cost Performance Index is used in various Project Management reports.
Cost Performance Index = Budgeted Cost of Work Performed/Actual Cost of Work Performed
>1 indicates costs are under budget
<1 indicates costs are over budget
In the equation above, the Budgeted Cost of Work Performed is based on the design cost estimates.