To determine the dates when the next PM procedure is due, run the Define PM Schedule Dates by PM Schedules task or the Generate PM Work Orders task. These tasks include an option that executes the program's scheduling routine, which does the following:
The following outlines how upcoming due dates are determined.
The routine works with the following date fields:
Field Title | Field Name | Table | Explanation |
---|---|---|---|
Due Date From? | due_date_from | PM Schedules | Determines whether the scheduling routine uses dates from the SLA or the PM Schedule record. |
Date of Last PM | date_last_completed | PM Schedules |
The scheduling routine completes this field with the value of the Date Work Completed field of the most recently completed work request generated for this schedule. For floating scheduling, the routine uses this field to determine future PM dates. The system updates this value whenever PM work is planned, generated, completed, moved, or cancelled. |
Date for First PM | date_first_todo | PM Schedules | For fixed scheduling, the scheduling routine determines future PM dates by working from this date. |
Calc. Date for Next PM | PM Schedules |
The system updates this value whenever when you (or the system) generates a PM work order, generates PM Schedule dates, completes a PM work order, or modifies/cancels/deletes a PM Schedule Dates record. This value can represent either a planned PM Date or an open work order, and it may be a date in the past if it represents an open work order that is late or missed. It can be blank if there are no more work orders or planned dates after the last work order is completed (this will be common for Floating schedulings). The system updates this value based on this logic:
|
|
Manual Date for Next PM | PM Schedules | If you complete this field, the scheduling routine completes Calc. Date for Next PM with this value and ignores the schedule definition. | |
Days Late Boundary | days_late | PM Schedules |
When you generate PM Schedule Dates, contributes to the value of PM Date – Latest. Specifies the number of days after the scheduled date that the work can be executed without causing a problem. |
Days Early Boundary | days_early | PM Schedules |
When you generate PM Schedule Dates, contributes to the value of PM Date – Earliest. Specifies the number of days before the scheduled date that the work can be executed without causing a problem. |
PM Date - Latest | date_latest | PM Schedule Dates |
The scheduling routine calculates this based on the Days Late Boundary value. A NULL value means that the routine can move this job back until the next date for this PM Schedule. pmsd.date_latest = pmsd.date_todo + pms.days_late
On the PM Planner's calendar, the PM Date Latest and the PM Date Earliest dates appear as brackets surrounding the PM Date rectangle . They are informational only, meaning you can still move a PM Date beyond these dates. If you set Due Date From? to be SLA, the scheduling routine uses the value of PM Date – Latest as the due date of the work request . |
PM Date - Earliest | date_earliest | PM Schedule Dates |
The scheduling routine calculates this based on the Days Early Boundary value. A NULL value means that the routine can move this job back until the prior date for this PM Schedule.
On the PM Planner's calendar, the PM Date Latest and the PM Date Earliest dates appear as brackets surrounding the PM Date rectangle. They are informational only, meaning you can still move a PM Date beyond these dates. |
PM Date - Original | date_orig_todo | PM Schedule Dates | The scheduling routine completes this field with the same values as PM Date (pmsd.date_todo). This "original" date serves as a means of preserving information about a PM Schedule date if a maintenance manager changes the PM Date. |
PM Date | date_todo | PM Schedule Dates | The scheduling routine completes this field based on the schedule you defined. It copies this value to PM Date Original. |
PM Date Status | vf_pmsd_status | PM Schedule Dates |
The PM Date Status is a virtual field that the scheduling routine completes by examining fields in the PMSD record. The values are:
|