Archibus Cloud / Maintenance / Preventive Maintenance / Generate PM Work Orders
Maintenance / Preventive Maintenance / Maintenance Manager / Generate PM Work Orders

Manually Generating PM Work Orders

At periodic intervals, you must determine the upcoming maintenance work and have the system generate work orders for executing this work by running the Generate PM Work Orders task. (Alternately, you can have the system automatically generate work orders, based on work order generation rules that you define.)

With the Generate PM Work Orders task, you instruct the system to generate work requests -- complete with required parts, labor, and tools -- based on the PM procedures and schedules that come due during the specified date range. The action groups the generated work requests onto work orders based on grouping criteria that you specify.

If you have defined preventive maintenance SLAs, the system matches work requests to the appropriate SLA, which dictates the time to complete, time to respond, craftsperson assignment, and if the generated work order should be auto-issued.

The basic process is:

  1. Specify the work for which you will generate work orders.
  2. Generate work orders.
  3. View generated work orders.

Note: As you work through this task, you will be working with either location work or equipment work. The task presents separate tabs for generating equipment or location work orders. Once you select a tab, the process is the same.

Time Zones and Generating Work Requests

The system bases dates and times for creating and issuing work requests for resolving PM work using the "current local date and time" of the individual work locations or the locations of the individual equipment items that need attention. For implementations with multiple sites across multiple time zones, this behavior enables the system to accurately handle times and dates of work requests regardless of the system time and date of the application server or the database at the time that the work is defined.

For example, suppose you are in your home office and you assign a procedure to all equipment items of a particular standard, with many of these equipment items being located in offices with time zones other that yours. Since the actual maintenance will occur in sites whose time zones are different than the time zone from which you are defining the work, when you generate work requests and work orders to service them, the system uses the time zones of the equipment locations for all times and dates; it does not use the time zone from which you are defining the work.

As the work requests travel through the Preventive Maintenance system, the system ensures that the work requests are processed according to the current local time and date of the work location or equipment location. For example, if you are using a preventive maintenance SLA, the system calculates the escalation dates based on the current local date of the work location.

Note: The Date to Perform in PM is based on the PM scheduling routine, and is not related to the time zone functionality.

Step 1: Specify the Work for which you will Generate Work Orders

The first step is to specify the work (the PM Schedules) for which you want to generate work orders.

  1. Run the Generate PM Work Orders task and choose the Equipment or Location tab, depending on whether you want to generate work orders for equipment tasks or location tasks.
  2. Optionally, you can specify the location (site, building , or floor), trade, and schedule group for which to generate work. You can set as many of these fields as apply to your situation. For example, you can generate work orders for servicing equipment that is located on a specific floor and serviced by a certain trade. Or, you might want to generate work for those tasks of the same grouping code. Leave these options blank to generate work orders for all upcoming work due during the specified date range.
  3. Enter a date range during which PM schedules will come due.
  4. Click Next to move to the Group and Generate Work Orders tab.

Note: For information on the scheduling routine that the program uses to determine upcoming work, see Understanding the PM Scheduling Routine.

Note: In addition to determining upcoming work with this task, you can run the Define PM Schedule Dates by PM Schedules task and choose the Generate option. You can then review the PM Schedules by running the Review PM Schedules task.

Step 2: Specify Work Order Groupings and Generate Work Orders

For the date range and other criteria that you specified in Step 1, the system determines the possible PM work due during this time frame.

The system will generate one work request for each PM schedule due during the specified date range. Use the below Group PM Schedules By options to determine how to group the generated work requests onto work orders. You may choose one of the following options:

If you wish, you can set one or both of the following options:

When through with the above options, click Generate in the upper right corner. The system generates work orders and presents the Generate PM Work Orders Job Report window; since the work order generation process can take time, you may wish to let this process run while you move onto other tasks.

For information on the exact actions that the system follows to generate the work orders, see Understanding PM Work Order Generation Routine.

Step 3: View Generated Work Orders

Once you generate your work orders, you will want to view them. There are two methods of doing so:

Note the following about your work orders:

Next

The generated work orders can now be assigned to craftspersons to execute the work and then they must be issued so that the work can be done. Assigning craftspersons and issuing work orders is typically done by a supervisor. See Preventive Maintenance Supervisor Overview.

If you have developed an SLA to govern the work orders, your work order may already have an assigned craftsperson or may be auto-issued upon generation.